Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Premier Pitches

Construction of SISGrass stitched hybrid turf stadium pitch

Nottingham Forest Football Club, The City Ground Stadium

Introduction

The iconic City Ground stadium

You can feel the history at the iconic City Ground stadium, home to a club with 11 major honours to its name, including 2 European trophies. Under the leadership of their famous manager Brian Clough, the club’s history is something to be admired.

Following major investment by the owners at the training ground in 2022, the decision was made to update the 30 year old pitch with a new stitched hybrid construction.

The club employed Charles Henderson of PSD to advise on the project as Turfgrass Consultant.

Following the success of delivering the training ground pitches, the club employed Premier Picthes to carry out the re-construction. Work started in May 2023.

Project challenges

Ground conditions

The existing 30 year old pitch overlaid ancient landfill, so excavating into original ground threw up some interesting finds.

Excavating drainage and service trenches uncovered ash, soft ground, old pottery, bricks and concrete. All had to be dealt with efficiently to maintain the tight programme.

Our approach

An extensive pitch re-construction

The scope of work comprised the following:

  • Excavate to remove 450mm depth from the entire surface of the existing pitch, load onto lorries and remove from site to tip/recycling
  • Cut and fill earthworks to create new pitch levels and installation of primary drainage with pumped outlet
  • Installation of new irrigation and undersoil heating systems
  • Supply and install new gravel raft drainage layer, lower sand layer and upper rootzone surface complete with nutrient retentive amendments
  • Cultivation, fertiliser applications and seeding carried out in conjunction with MJ Abbott
  • Installation of SISGrass stitched hybrid pitch reinforcement system
  • Excavate to remove surrounds and reconstruct with stone layers and new 3G SIS turf carpet complete with rubber infill.

Outcomes

A successful re-construction that plays as expected

The pitch was successfully grown in by head groundsman Ewan Hunter, who continued to maintain a high standard during the first season’s use.

The pitch played as expected during its first season, reacting well to intense use at times, across all club competitions and training sessions.