Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Premier Pitches

Construction of SISGrass hybrid turf training pitch

Southampton Football Club, Staplewood Campus

Project summary

New training pitch for the Saints

MJ Abbott successfully tendered the project to reconstruct Pitch 2 from a fibre surface to hybrid. PSD were employed to oversee construction, materials specification approval and performance testing.

The scope of works comprised:

  • Excavate 150mm depth from existing pitch area of 11,700m²
  • Fibre material was stripped separately and transported to a local club for re-use
  • Grade retained lower sand profile to re-establish pitch levels
  • Import and spread 50mm depth of compatible sand and 100mm depth of approved rootzone
  • Pitch extension construction, comprising irrigation, drainage, gravel raft, lower and upper rootzone
  • Installation of amendments, preparation of surface and seeding
  • Installation of SISGrass hybrid pitch reinforcement system
  • Overseeding surface following stitching
  • Construction of concrete retaining wall and installation of gates.